The design of the A8 motorway - Wrocław by-pass with a bridge over the Odra River: Wrocław

START YEAR: 2008
END YEAR: 2011

Investment project: “The design of the A8 motorway - Wrocław by-pass with a bridge over the Odra River”
Value of the investment project: PLN 576.000.000,00

Contractor: MOSTOSTAL WARSZAWA S.A. Implementation in the years 2008 - 2011.

Rędziński bridge was built as part of the Wrocław motorway by-pass (AOW). Our biggest ever polymer concrete cornice boards type MG28, 1700mm high and 1980mm long, are mounted on the structure.

One cornice weights approx. 800 kg.